Bizarre: Data centres have a total of 15 GW (15,000 MW) in queue for electricity connections in the Netherlands, grid operators just disclosed. That's roughly the current average national power use!
Replies (1)
-
@Sustainable2050@mastodon.energy 2026-10-15 19:03
Assuming that they would actually get to build those data centres and get the connections, the new data centres would (at 90% capacity factor) use around 120 TWh/year, as much as all companies and households together use now.