Elektrine lite

← Feed

@Sustainable2050@mastodon.energy

2026-10-15 19:02 UTC

Bizarre: Data centres have a total of 15 GW (15,000 MW) in queue for electricity connections in the Netherlands, grid operators just disclosed. That's roughly the current average national power use!

Replies (1)

  • Assuming that they would actually get to build those data centres and get the connections, the new data centres would (at 90% capacity factor) use around 120 TWh/year, as much as all companies and households together use now.

    Open ##5219279