@ar387@mstdn.social The more important question is how many years did that wind farm run before needing to be decommissioned. When we compare various energy systems this is an important consideration.

Replies (1)

  • @Landa@graz.social 2026-09-04 11:23

    @icanbob@techhub.social Phase 1 was operating since 1995 and ran 28 years until 2023. According to https://www.scottishpowerrenewables.com/onshore-new/onshore-scotland/wind-scotland/operational-windfarms/hagshaw-hill-windfarm only Phase 1 turbines will be replaced. @ar387@mstdn.social